Building Overview

Milestones

skyline

2006

Aerial view of the Makati skyline

02

May 11, 2009

Groundbreaking

03

December 2009

Excavation

04

February 2010

Start of construction of mat foundation

05

December 2010

Work on basement and superstructure

06

March 2011

Installation of the curtain wall

07

September 2011

Topping-out

glass

June 2012

Completion of the All-glass Facade

lobby

July 2012

Completion of Fit-outs

aug

September 2012

Completion of the 2,500 sq.m garden

dsc1168

November 8, 2012

Inauguration of the Zuellig Building Office Tower

Terraza

June 2013

Completion of the retail annex with the Terraz Bistro and Meeting Rooms and LaZa food pavilion

leed

July 16, 2013

LEED Platinum certification by the US Green Building Council